was founded in May 2015. As a port with access to
                                                       the Barents Sea, Murmansk was chosen to be its lo-
                                                       cation due to convenient logistics: cargo ships moor
                                                       here all year round, and LNG train platforms can be
                                                       towed from here to any location in the Russian Arctic.
                                                          LNG Construction Center lists as a large-scale
                                                       strategic investment project of the Murmansk Oblast.
                                                       Earthwork and blasting operations started on the
                                                       construction site in 2017. Land-levelling required the
                                                       removal of more than 18 million cubic meters of soil
                                                       and blasting of around 9 million cubic meters of rock.
                                                       Alongside this, the waters of the Kola Bay received 15
                                                       hectares of artificial islands.
                                                          The first to be built were GBS manufacture facili-
                                                       ties, concrete plants, and hydraulic structures – dry
                                                       docks, berths, and earth-fill cofferdams. Dry Dock 1
                                                       had its first piles driven into the seabottom in 2018.
                                                       In November 2019, the first GBS received its bottom
                                                       plate, which was installed with its first block module
                                                       in May 2021. According to Dmit-
                                                       ry Zagranichny, LNG Construc-
                                                       tion Center was commissioning     «Арктик СПГ 2» – первый
                                                       its phases on a last-minute basis   проект, оборудование для
                                                       but did manage to stay on schedule
                                                       with Arctic LNG 2.                которого создают на ЦСКМС,
                                                          The construction of the up-    но не последний
                                                       per structure modules started six   Arctic LNG 2 is the first, and
                                                       months after that of GBS and in-
                                                       volved a team of 27,000. Suppliers   certainly not the last, project
                                                       of materials and equipment num-   Center manufactures for
                                                       bered more than a hundred, of
                                                       which  90%  were  domestic  manu-
                                                       facturers.
                                                          Center used as its general de-
                                                       signer Saint Petersburg-based Lenmorniiproject. As-
                                                       sisting it were companies is St. Petersburg, Ufa, Vol-
                                                       gograd, Yekaterinburg and other cities. The project
                                                       documentation was submitted to state review in 2017
                                                       and required no corrective action.
                                                          As large as 18-storey buildings

                                                          Some of the design solutions used on Center are
                                                       genuinely special. One example is the building of the
                                                       shop for final assembly of the upper structures, which
                                                       is the largest building ever built in Eurasia and the
                                                       world’s third largest in terms of work space (9 mil-
                                                       lion cubic meters). It is 92 meters high and has on
                                                       its sides 70 m high sliding gates for passing modules
                                                       as large as 18-storey buildings. Installed inside are